Tynagh Outage 15.06.2018
Publication date: 23:08 15/06/2018
Message ID: TYN_000001_01
Event Status: open
Type of unavailability: Production Unavailability
Type of event: unplanned
Time/date of incident start: 22:14 15/06/2018
Estimated time/date of incident end: 01:00 16/06/2018
Unit of measurement: MW
Unavailable capacity: 404
Available capacity: 0
Installed capacity: 404 MW
Reason for unavailability: Suspected Gas Turbine Water Injection system lockout which caused high exhaust temperature trip
Remarks:
Fuel Type: Fossil Gas
Bidding Zone: 10Y1001A1001A59C
Affected Asset or Unit: Tynagh Production Unit
Affected Asset or Unit EIC: 47W000000000172K
Market Participant: Tynagh Energy Limited